Project Summary
NBA All-Star's home bowling alley has “Red Hot Allusion” lanes with grey markings and flame glow graphics that become visible under UV lighting. Custom gray pins and black pearl guest balls.
Kensington Custom Homes
Southlake, Texas
NBA All-Star's home bowling alley has “Red Hot Allusion” lanes with grey markings and flame glow graphics that become visible under UV lighting. Custom gray pins and black pearl guest balls.
Kensington Custom Homes
Southlake, Texas
The answer to this question gets its own cute little flow chart on its own web page. See our Process page.
It can take 4 months or more to get the equipment ordered, prepped, and ready to ship.
A pair of lanes take about one week to install. Single lanes take about six days, and 4-lane projects take about 11 days.
The window of opportunity is after HVAC is up and running but before flooring is installed.